HomeMy WebLinkAbout06.30.26 Board Correspondence - FW_ Compliance Directives issued in FERC P-2088-000From:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod;
Kitts, Melissa; Krater, Sharleen; Lee, Lewis; Little, Melissa; Pickett, Andy; Ritter, Tami; Stephens, Brad J.;
Sweeney, Kathleen; Teeter, Doug; Zepeda, Elizabeth
Cc:Loeser, Kamie; Cannon, Jamie
Subject:Board Correspondence - FW: Compliance Directives issued in FERC P-2088-000
Date:Tuesday, June 30, 2026 11:48:18 AM
Please see Board Correspondence -
Lewis Lee
Administrative Technician - Confidential
Butte County Administration
25 County Center Drive, Suite 200 • Oroville, CA 95965
T: 530.552.3326
www.buttecounty.ca.gov | lelee@buttecounty.ca.gov
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Tuesday, June 30, 2026 9:36 AM
Subject: Compliance Directives issued in FERC P-2088-000
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening
attachments, clicking on links, or replying..
On 6/30/2026, the Federal Energy Regulatory Commission (FERC), Washington D.C., issued this document:
Docket(s): P-2088-000
Lead Applicant: South Feather Water & Power Agency
Filing Type: Compliance Directives
General Correspondence
Description: Letter to South Feather Water and Power Agency providing comments on the 06/01/26 request for
work authorization for a fall protection system at South Fork Diversion Dam and Slate Creek Diversion Dam, part
of the South Feather Power Project under P-2088.
To view the document for this Issuance, click here
https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20260630-
3052__;!!KNMwiTCp4spf!HXJkVXpcL-1i40tkMnUcPzLnkEh3gfN5wmFepl_Rg0KBm9rE2s7hm04Q9boZfv-
CZ8dt85GaZazFekRxnnJ5AeMEzp8wbx-9vaD3$
To modify your subscriptions, click here:
https://urldefense.com/v3/__https://ferconline.ferc.gov/eSubscription.aspx__;!!KNMwiTCp4spf!HXJkVXpcL-
1i40tkMnUcPzLnkEh3gfN5wmFepl_Rg0KBm9rE2s7hm04Q9boZfv-
CZ8dt85GaZazFekRxnnJ5AeMEzp8wb4nDnuWE$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!HXJkVXpcL-
1i40tkMnUcPzLnkEh3gfN5wmFepl_Rg0KBm9rE2s7hm04Q9boZfv-
CZ8dt85GaZazFekRxnnJ5AeMEzp8wb20rakIl$
or for phone support, call 866-208-3676.
Comments and Suggestions can be sent to this email address: mailto:FERCOnlineSupport@Ferc.gov
FEDERAL ENERGY REGULATORY COMMISSION
Office of Energy Projects
Division of Dam Safety and Inspections –San Francisco Regional Office
June 30, 2026
In reply refer to:
Project No. 2088-CA
VIA FERC Service
Rath Moseley
General Manager
South Feather Water and Power Agency
2310 Oro Quincy Highway
Oroville, CA 95966-5226
Re:Request for Work Authorization for South Fork Diversion Dam and Slate Creek
Diversion Dam Fall Protection Project
Dear Mr. Moseley:
This is in response to a letter dated June 1, 2026,from Ms. Kristen McKillop that
submitted a request for work authorization for a fall protection system at South Fork
Diversion Dam and Slate Creek Diversion Dam, which are part of the South Feather
Power Project, FERC No. 2088. We have reviewed the submittal, and have the following
comment:
While the special inspector was named in the Quality Control and Inspection
Program (QCIP)and a resume provided, we note that the Design Engineer and
Construction Project Manager were not named. Resumes for all positions with
stop work or recommend stop work authority must be provided, and these were
missing for the Project Manager and Construction Project Manager.Update the
organizational chart to name these individuals and provide the required resumes
customized to match direct experience to other projects with a similar scope of
work to this project.
Provided that you address the above comment within 10 days of the date of this
letter, you are authorized to proceed with construction upon receipt of this letter. Failure
to adequately address our comment within 10 days will require a suspension of all work
until the comments are addressed.
During construction,we typically require monthly construction reports. However,
due to the short duration of this project, we will not require monthly construction reports.
2
Within 90 days of completion of construction of the facilities authorized by this
letter, or no later than December 29, 2026, you must file the following:
1.A final construction report, which addresses the applicable items in Enclosure 1.
2.The following construction certifications, which must be verified in accordance
with Title 18, Section 12.13 of the Code of Federal Regulations (18 CFR 12.13):
a.A certification by the Design Engineer that the project was constructed in
accordance with the design intent.
b.A certification by the Quality Control Manager that the inspection and testing
program resulted in the conclusion that the project was constructed in
accordance with the plans and specifications reviewed by us.
c.A certification by the Licensee (South Feather Water and Power Agency) that
the project was constructed in accordance with the design intent and in
accordance with the plans and specifications reviewed by us.
Sample certifications are given in Enclosure 2.
If the plans and specifications are revised during the construction process, it is
your responsibility to ensure that these changes are properly coordinated between the
Design Engineer, the Resident Engineer, the Project Manager, the FERC, and you, prior
to proceeding with the changes. Also, you are reminded that no changes may be made to
the operation of the project without first coordinating those proposed changes with the
FERC.
You are responsible for ensuring completion of any necessary environmental
coordination with resource agencies as well as the procurement of any federal, state, or
local permits required for the work.
File your submittal using our eFiling system at https://www.ferc.gov/ferc-
online/overview. When eFiling, select Hydro: Dam Safety; San Francisco Regional
Office from the eFiling menu. The cover page of the filing must indicate that the
material was eFiled. For assistance with eFiling, contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY).
3
We appreciate your continued efforts in this aspect of our dam safety program.If
you have any questions, please contact Mr.Cody Stephenson at (415)369-3308.
Sincerely,
Frank L. Blackett, P.E.
Regional Engineer
cc:
Erik Malvick -Division Manager
CA Dept. of Water Resources
Division of Safety of Dams
2720 Gateway Oaks Drive, Suite 300
Sacramento, CA 95833
c/o Shawn.Jones@water.ca.gov
Enclosures (2)
Items to be Addressed in Final Construction Reports for Enclosure 1
South Fork Diversion Dam and Slate Creek Diversion Dam Fall Protection Project
FERC No. 2088
FINAL CONSTRUCTION REPORTS FROM LICENSEES
The Final Construction Report should be submitted within 90 days of completion
of the work. This report should include all information pertinent to dam safety in a
concise form. It should be included in the project file and should be given to the
independent consultant for his or her safety inspection and analyses, if applicable. As
such, the report should contain a summary of information in each of the applicable
sections indicated below (the information was previously presented in the monthly
reports). Construction difficulties should be reported under the appropriate sections. For
conciseness, test results should be presented in a tabular format, with an indication of the
applicable standards. Finally, in those cases where there is nothing to report under a
specific heading, a statement of non-applicability will suffice.
1. General. Briefly present the reason for construction and description of the work with
dates of the beginning and end of construction. Include reservoir drawdown and filing
dates, and any findings regarding the original structure.
2. Foundations. Discuss the condition of the foundation (faults, etc.) and the treatment of
the foundation. Attach a foundation mapping.
3. Embankments. Describe the equipment and the types of materials used in filters and
fills. Attach gradation and compaction requirements and all test results.
4. Concrete work. Describe the equipment and the types of materials used in all concrete
work. Include all grout test results and describe any surface treatments.
5. Anchors. Present a summary of any drilling operations, including boring logs; results
of water pressure tests; anchor design calculations, design loads, and specifications;
results of grout tests; results of proof and performance tests; and a summary of the
acceptance criteria.
6. Instrumentation. Present plots of existing instrumentation readings taken during
construction if the readings are affected by the work. Include a plan and schedule for
calibration of all new instrumentation.
7. Drawings. Attach as-built drawings reduced in size to 8.5"x11" or 11"x17". The
drawings should include plan and section views, and details of the structures affected by
the new work. The plan and section views should show any new instrumentation that
was installed as part of the work.
Enclosure 2
CERTIFICATION
By Design Engineer
CERTIFICATION OF CONSTRUCTION PAGE 1 OF 3
FERC Project No.
Construction Project Description:
Design Drawings/Specifications:
Quality Control and Inspection Program (QCIP) dated:
This is a certification by the Design Engineer that the project was constructed in accordance
with the design intent.
*****************************************************************************
VERIFICATION
STATE OF CALIFORNIA ]
COUNTY OF ],SS:
The undersigned, being first duly sworn, states that he/she has read the above document
and knows the contents of it, and that all of the statements contained in that document are
true and correct, to the best of his/her knowledge and belief (per 18CFR Part 12,
Paragraph 12.13).
Design Engineer (Print Name)
Signature
[STAMP]
Sworn to and subscribed before me
this day of , 20
NOTARY PUBLIC [SEAL]
Enclosure 3
CERTIFICATION
By Quality Control Manager
CERTIFICATION OF CONSTRUCTION PAGE 2 OF 3
FERC Project No.
Construction Project Description:
Design Drawings/Specifications:
Quality Control and Inspection Program (QCIP) dated:
This is a certification by the Quality Control Manager that the inspection and testing program
resulted in the conclusion that the project was constructed in accordance with the plans and
specifications reviewed by the Commission.
*****************************************************************************
VERIFICATION
STATE OF CALIFORNIA ]
COUNTY OF ],SS:
The undersigned, being first duly sworn, states that he/she has read the above document
and knows the contents of it, and that all of the statements contained in that document are
true and correct, to the best of his/her knowledge and belief (per 18CFR Part 12,
Paragraph 12.13).
Quality Control Manager (Print Name)
Signature
[STAMP]
Sworn to and subscribed before me
this day of , 20
NOTARY PUBLIC [SEAL]
Enclosure 3
CERTIFICATION
By Licensee or Exemptee
CERTIFICATION OF CONSTRUCTION PAGE 3 OF 3
FERC Project No.
Construction Project Description:
Design Drawings/Specifications:
Quality Control and Inspection Program (QCIP) dated:
This is a certification by the Licensee or Exemptee that the project was constructed in
accordance with the design intent and in accordance with the plans and specifications reviewed
by the Commission.
*****************************************************************************
VERIFICATION
STATE OF CALIFORNIA ]
COUNTY OF ],SS:
The undersigned, being first duly sworn, states that he/she has read the above document
and knows the contents of it, and that all of the statements contained in that document are
true and correct, to the best of his/her knowledge and belief (per 18CFR Part 12,
Paragraph 12.13).
For Licensee or Exemptee (Print Name)
Signature
[STAMP]
Sworn to and subscribed before me
this day of , 20
NOTARY PUBLIC [SEAL]