HomeMy WebLinkAbout06.30.26 Board Correspondence - FW_ Dam Safety Compliance Report submitted in FERC P-2107-000 by Pacific Gas and Electric CompanyFrom:Clerk of the Board
To:Clerk of the Board; Connelly, Bill; Cook, Holly; Cook, Robin; Durfee, Peter; Jessee, Meegan; Kimmelshue, Tod; Kitts, Melissa; Krater, Sharleen; Lee, Lewis; Little, Melissa; Pickett, Andy; Ritter,
Tami; Stephens, Brad J.; Sweeney, Kathleen; Teeter, Doug; Zepeda, Elizabeth
Cc:Loeser, Kamie; Cannon, Jamie
Subject:Board Correspondence - FW: Dam Safety Compliance Report submitted in FERC P-2107-000 by Pacific Gas and Electric Company
Date:Tuesday, June 30, 2026 8:08:43 AM
Please see Board Correspondence -
Lewis Lee
Administrative Technician - Confidential
Butte County Administration
25 County Center Drive, Suite 200 • Oroville, CA 95965
T: 530.552.3326
www.buttecounty.ca.gov | lelee@buttecounty.ca.gov
-----Original Message-----
From: 'FERC eSubscription' <eSubscription@ferc.gov>
Sent: Tuesday, June 30, 2026 6:46 AM
Subject: Dam Safety Compliance Report submitted in FERC P-2107-000 by Pacific Gas and Electric Company
.ATTENTION: This message originated from outside Butte County. Please exercise judgment before opening attachments, clicking on links, or replying..
On 6/30/2026, the following Filing was submitted to the Federal Energy Regulatory Commission (FERC), Washington D.C.:
Filer: Pacific Gas and Electric Company
Docket(s): P-2107-000
Lead Applicant: Pacific Gas and Electric Company
Filing Type: Dam Safety Compliance Report
Description: Pacific Gas and Electric Company submits Joshua Brake's resume for the additional inspector of the project to replace the lifting chains and request for FERC's
authorization re the Poe Dam of the Poe Hydroelectric Project under P-2107.
To view the document for this Filing, click here https://urldefense.com/v3/__https://elibrary.ferc.gov/eLibrary/filelist?accession_num=20260630-
5039__;!!KNMwiTCp4spf!Fq3LuD6AfS3G8G3Ym8EDNLPqWh74sJSvqSUUSX34_mAZQb3Zierl7qN5f7xgmxxy1-uprjdVsoFXNDFehXgQhlm_rs0lOt2zEz5I$
To modify your subscriptions, click here:
uprjdVsoFXNDFehXgQhlm_rs0lOpE6fH47$
------------------------------------------------------------------------
Please do not respond to this email.
Online help is available here:
https://urldefense.com/v3/__http://www.ferc.gov/efiling-help.asp__;!!KNMwiTCp4spf!Fq3LuD6AfS3G8G3Ym8EDNLPqWh74sJSvqSUUSX34_mAZQb3Zierl7qN5f7xgmxxy1-
uprjdVsoFXNDFehXgQhlm_rs0lOl28n4HS$
or for phone support, call 866-208-3676.
Document Accession #: 20260630-5039 Filed Date: 06/30/2026
Power Generation 300 Lakeside Drive
Oakland, CA 94612
Mailing Address:
P.O. Box 28209
Oakland, CA 94604
June 29, 2026
Via Electronic Submittal (E-File)
Frank L. Blackett, P.E., Regional Engineer
Federal Energy Regulatory Commission
Division of Dam Safety and Inspections
100 First Street, Suite 2300
San Francisco, CA 94105-3084
RE: Poe Hydroelectric Project, FERC No. 2107-CA
Poe Dam, NATDAM No. CA00328
Replacement Lifting Chains for Flood Gate – Additional Inspector Resume
Dear Frank L. Blackett:
This letter presents an additional inspector resume for the project to replace the lifting chains at
Poe Dam, which is part of Pacific Gas and Electric Company’s (PG&E) Poe Hydroelectric Project,
Federal Energy Regulatory Commission (FERC) No. 2107. PG&E submitted the original project
design package to FERC in a letter dated June 15, 2023, and FERC authorized construction in a
letter dated March 4, 2024. In a letter dated February 28, 2025, PG&E requested an extension of
time to submit the final construction report by February 28, 2027; FERC accepted the request in a
letter dated May 9, 2025.
The resume for the proposed inspector, Joshua Brake, is provided in (Enclosure 1).
PG&E respectfully requests authorization of the additional inspector. Should you have technical
questions concerning this matter, please contact Chris Tomes, dam safety engineer for PG&E, at
(818) 584-9944. For general questions, please contact Andrew Garcia, license coordinator for
PG&E, at (530) 228-8990.
Sincerely,
Robert O. Ellis, P.E., G.E.
Deputy Chief Dam Safety Engineer
Enclosure:
1. Inspector Resume – Joshua Brake, Senior Inspector
Document Accession #: 20260630-5039 Filed Date: 06/30/2026
ENCLOSURE 1
Document Accession #: 20260630-5039 Filed Date: 06/30/2026
Joshua Brake
Senior Inspector
Email: JR5C@PGE.com
Power Generation │ 245 Market Street │ San Francisco, CA 94105 Phone: (916)297-3289
1
PROFESSIONAL SINCE: 1999
EDUCATION
•Sierra High School Graduate
•Millwright Apprenticeship Graduate
TRAINING
•Introduction to Dams
•PG&E Dam Safety Program
•Basic Dam Surveillance &
Monitoring
•Basic Dam Inspections
•Basic Dam Maintenance
•Dam Surveillance and Monitoring
•Inspection of Embankment Dams
•Inspection of Concrete and
Masonry Dams
•Scaffolding
•Haz-Mat
•Asbestos
•Safety at Heights
•Lock-Out Tag-Out Procedures
•LOTO Trained
•PG&E Confined Space,
Competent Person Training
•NERC CIP-004-R2 Security
Training Program
•Ladder Safety
•Wilderness First Aid
•Fall Protection Competent Person
Training
•Construction Safety Associate-
Level 1
PROFESSIONAL SUMMARY
Mr. Brake has 26 years in the construction industry, with the last 19
months of the inspection and construction experience with a variety
of PG&E Hydro projects. Prior to PG&E employment Mr. Brake
worked as a journeyman / field supervisor Millwright in Hydro power
generation facilities and a Senior Power Generation Inspector here at
PG&E. Experience includes:
•Construction and Maintenance Related to
Powerhouses, Switchyards, Rebuilding and Aligning
Hydro Generators, Fabricating Steel Structures
•Structural Steel, Steel Foundation/Reinforcement
•Security Fencing
•Rigging
•Penstock Inspection
•Radial Gate Inspection.
•NDE Inspections.
•Welding
•Paint Coatings
•Concrete Embed Anchors
•Maintenance of stop log gates
•Construction and maintenance on underground facilities
•Coring Through Concrete and Stone Structures
•Installation of Large Cone Valves & Butterfly Valves
•Drilling and Installation of Piezometer’s.
•Underwater/diving operations related
construction/maintenance
•Dam maintenance and construction.
•Performed construction engineering inspection and
construction materials testing and laboratory testing services
to project specifications including:
o Concrete/shotcrete placement, and testing
o High-and-low pressure grouting operations and epoxy
injection
o Reinforcing steel placement
o Structural steel erection including high strength bolting
and welding
o Post-installed anchors and dowels
o Appurtenant construction related to gate/valve/debris
barrier replacement.
Document Accession #: 20260630-5039 Filed Date: 06/30/2026
Joshua Brake
Senior Inspector
Email: JR5C@PGE.com
Power Generation │ 245 Market Street │ San Francisco, CA 94105 Phone: (916)297-3289
2
CERTIFICATIONS
•OSHA 510 Standards for Construction Industry
•OSHA 7505 Introduction to Incident (Accident) Investigation
•OSHA 7845 Recordkeeping Rule Seminar
•OSHA 3115 Fall Protection
•OSHA 3015 Excavation, Trenching and Soil Mechanics
•OSHA 2264 Permit Required Confined Space Entry
•OSHA 5109 CAL/OSHA Standards for Construction Industries
•40-Hour HAZWOPER Hazardous Waste Operations and Emergency Response
•OSHA 10
•OSHA 30
•PG&E UTV Operations
•First-Aid/CPR/AED
PROJECTS
•Pit 5 Unit 3 Stop Log Gate Sealing 2026
PG&E SENIOR INSPECTOR
The project scope involved conducting underwater inspections of the tailrace stop log
gate tracks using certified dive operations prior to gate lowering, followed by detailed
inspections of the gates once set into position and before dewatering activities
commenced.
Responsibilities included inspection for compliance with project drawings, quality
control inspection program, and contract specification for:
-Staffing and oversight of the inspection support team responsible for managing
project quality control, worker safety, and permit adherence.
-Inspection verification that construction means and methods conformed to the
project drawings specifications and QCIP
-Stop work authority.
•Cresta Stop Log Gate Sealing 2026
PG&E SENIOR INSPECTOR
The project scope involved conducting underwater inspections of the tailrace gate
tracks using certified dive operations prior to gate lowering, followed by detailed
inspections of the gates once set into position and before dewatering activities
commenced.
Responsibilities included inspection for compliance with project drawings, quality
control inspection program, and contract specification for:
Document Accession #: 20260630-5039 Filed Date: 06/30/2026
Joshua Brake
Senior Inspector
Email: JR5C@PGE.com
Power Generation │ 245 Market Street │ San Francisco, CA 94105 Phone: (916)297-3289
3
-Staffing and oversight of the inspection support team responsible for managing
project quality control, worker safety, and permit adherence.
-Inspection verification that construction means and methods conformed to the
project drawings specifications and QCIP
-Stop work authority.
•Strawberry Lake LLO ROV Inspection 2026
PG&E SENIOR INSPECTOR
The project scope involved conducting underwater ROV inspections on the Interior and
exterior of the Low-Level Outlet tower using certified ROV dive operations.
Responsibilities included inspection for compliance with project drawings, quality
control inspection program, and contract specification for:
-Staffing and oversight of the inspection support team responsible for managing
project quality control, worker safety, and permit adherence.
-Inspection verification that construction means and methods conformed to the
project drawings specifications and QCIP
-Stop work authority.
•Kerckhoff Dam Replace Gate Chains 2026
PG&E SENIOR INSPECTOR
The project scope of work consisted of diving inspection of the Kerckhoff Dam plunge
pool, downstream face and upstream face of the dam, removal and replace gate chains
shackles, shackle plates and all associated hardware.
Responsibilities included inspection for compliance with project drawings, quality
control inspection program, and contract specification for:
-Dive operations
-Mechanical chain replacement
-Stop work authority
•Rock Creek Dam Cofferdam and Drum Gate Repairs 2025
PG&E SENIOR INSPECTOR
The project scope consisted of installation of the new drum gate modular vertical truss
cofferdam system and improvements to the existing two, 124-feet long by 28-feet high
drum gates and mechanical appurtenances. Work included replacement of the existing
gate seals, hoses, reconstruction of the stilling wells, replacement of 12 auxiliary supply
pipe butterfly valves, and industrial coatings.
Document Accession #: 20260630-5039 Filed Date: 06/30/2026
Joshua Brake
Senior Inspector
Email: JR5C@PGE.com
Power Generation │ 245 Market Street │ San Francisco, CA 94105 Phone: (916)297-3289
4
Responsibilities included inspection for compliance with project drawings, quality
control inspection program, and contract specification for:
-Inspection verification of means and methods used and materials placed met the
project design drawings, QCIP, and specifications
-Cofferdam installation and removal
-Water bypass pumping
-Stilling well dredging
-Dive operations
-Post-installed anchors and dowels
-Field sampling and testing of plastic concrete and grout for properties and
compressive strength test specimens
-Concrete coring
-Mechanical piping and valve replacement
-Industrial coating
-Stop-work authority
•Kerckhoff 2 Runner Cavitation Weld Repair 2025
PG&E SENIOR INSPECTOR
Work scope included Providing oversight for contractor excavating out cavitation on
runner. Performed visual checks as directed by ATS. Documented all areas needing
repairs and repairs made.
Responsibilities included inspection for compliance with project drawings, quality
control inspection program, and contract specification for:
-Inspection verification of means and methods used, materials placed met the
project design drawings, QC, and specifications.
-Inspection of weld repair.
-Structural steel fabrication and welding in accordance with AWS D1.1 and D1.5
-NDE testing
-Stop work authority.
•Belden TSV Refurbishment 2024 to 2025
PG&E SENIOR INSPECTOR
The project scope included removal of TSV trunnions, inner seals and seats, associated
piping and electrical components, replacement of inner seals and seats, installing new
trunnions, inner seats and seals then pressure test.
Document Accession #: 20260630-5039 Filed Date: 06/30/2026
Joshua Brake
Senior Inspector
Email: JR5C@PGE.com
Power Generation │ 245 Market Street │ San Francisco, CA 94105 Phone: (916)297-3289
5
Responsibilities included inspection for compliance with project drawings, quality
control inspection program, and contract specification for:
-Oversight and inspection support for managing project quality control, worker
safety, training and permit adherence.
-Inspection and testing verification that construction means, methods, and
materials conformed to the project drawings specifications and QP.
-Mechanical and electrical appurtenances.
-Confined space entry, hot work permit, testing and policy adherence.
-Materials and processes used for application of epoxy and coatings associated
with repair of the paint removal both inside and outside of the TSV.
-Stop work authority.
•Belden Replace Seal Rings 2024 to 2025
PG&E SENIOR INSPECTOR
The project scope included disassembly of unit, remove DT, runner, throat ring, upper
and lower rotating seals, and stage runner at powerhouse facility. Remove and replace
upper and lower non-rotating seals. After the seal rings were replaced, the unit was
reassembled and realigned.
Responsibilities included inspection for compliance with project drawings, quality
control inspection program, and contract specification for:
-Oversight of the inspection support team responsible for managing project
quality control, worker safety, and permit adherence
-Inspection and testing verification that construction means, methods, and
materials conformed to the project drawings specifications and QP.
-Tensioning of anchor bolts
-Structural steel, high strength bolting.
-Structural steel fabrication and welding in accordance with AWS D1.1 and
D1.5.
-Precision measuring and setting clearances.
-Stop work authority.
•Belden Draft Tube Cavitation Repair 2024 to 2025
PG&E SENIOR INSPECTOR
The project scope included removal of the draft tube, stage outside. Removal of the
cavitation and the (4) four vortex baffles inside the daft tube.
Responsibilities included inspection for compliance with project drawings, quality
control inspection program, and contract specification for:
Document Accession #: 20260630-5039 Filed Date: 06/30/2026
Joshua Brake
Senior Inspector
Email: JR5C@PGE.com
Power Generation │ 245 Market Street │ San Francisco, CA 94105 Phone: (916)297-3289
6
-Oversight and inspection support for managing project quality control, worker
safety, training and permit adherence.
-Inspection and testing verification that construction means, methods, and
materials conformed to the project drawings specifications and QP.
-Hot work permits.
-Inspections for welding and coatings.
o Welding inspections. NDE, UT, MT inspections.
o Coatings, inspections, holiday testing and mill thickness checks.
-Materials and processes used for application of epoxy and coatings associated
with welding repair.
-Structural steel fabrication and welding in accordance with AWS D1.1 and D1.5
-Stop work authority.
•Belden Stop Log and Intake Gate Sealing. 2024
PG&E SENIOR INSPECTOR
The project scope involved conducting underwater inspections of the tailrace gate
tracks using certified dive operations prior to gate lowering, followed by detailed
inspections of the gates once set into position and before dewatering activities
commenced.
Responsibilities included inspection for compliance with project drawings, quality
control inspection program, and contract specification for:
-Staffing and oversight of the inspection support team responsible for managing
project quality control, worker safety, and permit adherence
-Inspection verification that construction means and methods conformed to the
project drawings specifications and QCIP
-Stop work authority.
Document Accession #: 20260630-5039 Filed Date: 06/30/2026